Aker Solutions order Power to Heat system for Troll C

news-details

Equinor awarded the project worth up to NOK three billion with Aker Solutions to secure shore power for Troll B and C. PARAT was chosen to deliver the High Voltage Electrode Hot Water Boiler module to be installed on Troll C.

PARAT Halvorsen AS will supply the turnkey EX-certified 6MW Electrode Hot Water Boiler module to Troll C. The eBoiler will have an 11kV connection, a design pressure of 12 barg and a 191,7°C design temperature. PARAT will also include Heat Exchanger, Circulation pump, Feedwater Pump, Control System and Chemical Dosing unit on the skid.

One part of the TWEL (Troll West Electrification) Project is to replace the Waste Heat Recovery Unit with a High Voltage Electrode boiler. PARAT has been awarded the contract for supplying the complete turn-key module, to be delivered in April 2024.

The boiler module will consist of a 6MW High-Voltage Electrode hot water boiler that will take over as the heating source for the heating medium circuit after the shut-down of the gas turbine. The installation will contribute to reducing CO2 emissions significantly with power from shore.

The module will have a footprint of 8.8x5m and an approximate lifting weight of 38 tons. It shall be designed for outdoor installation and EX-certified for installation in hazardous area zone II. All these factors combined make it a highly complex project.
Aker Solutions order Power to Heat system for Troll C from PARAT Halvorsen AS

Equinor awarded the project worth up to NOK three billion with Aker Solutions to secure shore power for Troll B and C. (Photo: Equinor)

PARAT was early involved with Aker Solutions and Equinor to develop a robust package design. As the module will consist of only one boiler, various measures have been taken to ensure as high availability as possible.

Due to a significant increase in the market for electrical boilers, PARAT has also taken measures to increase our capacity to produce offshore modules. The Troll C project will be performed in cooperation with Nymo, who will participate in different engineering disciplines, prefabrication of steel and piping and assembly of the components at the final stages.

PARAT has long-time expertise in designing turn-key boiler modules, and we see more and more advantages in getting involved in the early phases with the contractor and client. Together we can find the most optimal solutions for the complete installation.
Aker Solutions order Power to Heat system for Troll C from PARAT Halvorsen AS

(Photo: Equinor)

Note: PARAT will deliver the Power to Heat system on the Troll C-rig in the North Sea. (Photo: Øyvind Hagen/Equinor ASA)